Main works of this contract section:

The project adopts EPC mode. K17+464-k32+064, the main line is 14.6km long, two-way four lane, and 26m wide (including emergency Lane).

The project includes: Feicheng South toll plaza, Taoyuan toll plaza, Feicheng South Interchange, Taoyuan two-way service area, Zhaishan South tunnel, Wuqiangzhuang bridge and Zhaishan bridge.

Earth excavation 189194.5m³, reused earth 85027m³, borrow fill 965209.448m³, gravel for replacement 58987.3m³, geotextiles 201324.45m², precast blocks 4971.91m³, drainage ditch 11306m. Zhaishan South tunnel with 4268m and

two-way four lane, and 26m wide (including emergency Lane). Separated Interchange 1 no. (Feicheng South

Interchange), 1 large bridge: 1032m long and 25m high (Wuqiangzhuang bridge), 1 medium bridge: 366M long and 36m high (Zhaishan bridge)16 slab culverts. Cement stabilized graded gravel for 360mm-thichk subbase: 210049m²;

Cement stabilized graded gravel for 200mm-thichk subbase: 243194m²; Cement stabilized graded gravel for 200mm-

thichk base:237591.5m²; Cement stabilized graded gravel for 180mm-thichk base:200834.5m²; Cement stabilized graded gravel for 300mm-thichk base:12730m²; AC-20 medium-granular modified asphalt concrete for 60mm-thick lower pavement course:403545m²; AC-16C medium-granular modified asphalt concrete for 40mm-thick upper pavement course:403545m²; AC-16P medium-granular modified asphalt concrete for 50mm-thick wearing course:32606m²;

Price of this contractsection Original contract  RMB 666,544,302Actual AmountRMB664,336,849
Construction period of this contractsection  Original contract   23 months Actual Period 23 months